Condensed PMP Knowledge Map for Exam Day

Memorizing the PMBOK alone is rarely enough; you must practice situational questions. Below is a distilled cheat-sheet arranged by knowledge area, focusing on what the exam actually tests.

  1. Foundational Concepts

  • Phase-gate = go / no-go checkpoint.
  • Hybrid lifecycle = Predictive + Adaptive.
  • Adaptive = Iterative + Incremental; deliverables accepted each iteration.
  • Project success criteria agreed with sponsor & key stakeholders.
  • Benefits management plan: target benefits, strategic alignment, benefit owner.
  1. Operating Environment

  • Conflict over shared expert → consult expert + negotiate with other PM.
  • Org structures: Functional (dual authority), Matrix (resource sharing), Projectized (PM authority high).
  • PMO types: Suportive, Controlling, Directive.
  • Sponsor funds; escalate beyond PM’s control.
  1. Integration

  • All changes must be formal; unauthorized work → stop → follow change process.
  • Issue log created during Direct & Manage Project Work.
  • Close Project = administrative + financial + legal closure; contract closure per contract.
  • Configuration control = technical specs; change control = baselines.
  1. Scope

Process flow: Plan Scope → Collect Requirements → Define Scope → Create WBS → Validate Scope → Control Scope.

  • Scope baseline = scope statement + WBS + WBS dictionary.
  • Adaptive: backlog grooming each iteration.
  • Rolling wave planning = near-term detail, future high-level.
  • Requirement traceability matrix links each need to deliverable & status.
  1. Schedule

Sequence: Plan Schedule → Define Activities → Sequence → Estimate Durations → Develop Schedule → Control.

  • Fast-tracking = perform activities in parallel; first check dependencies.
  • Resource leveling may alter critical path; resource smoothing does not.
  • Three-point estimate (Beta): (O + 4M + P) / 6; σ = (P – O) / 6.
  • Agile: story points for size; velocity measures throughput.
  1. Cost

  • Cost baseline = direct cost + contingency reserve.
  • Total funding requirement = baseline + management reserve.
  • EV > PV → ahead of schedule; EV < AC → over budget.
  • TCPI = (BAC – EV) / (BAC – AC); lower is easier.
  1. Quality

  • Plan Quality: define standards & how to demonstrate compliance.
  • Manage Quality: process improvement, audit non-conformance.
  • Control Quality: verify deliverables meet requirements.
  • Quality cost categories: prevention, appraisal, internal failure, external failure.
  • Control chart: UCL/LCL (process voice), USL/LSL (customer voice).
  1. Resources

  • Staff skill gap → training, reassignment, or revise plan.
  • Resource calendar = availability of people & equipment.
  • Control Resources (Monitoring) = physical resources; Manage Team (Executing) = people.
  • Team-building most efffective for relationship issues.
  1. Communications

  • Too much unstructured info → revise communications management plan.
  • Meeting interruptions → ground rules not enforced.
  • Uninformed stakeholder → update communications plan.
  1. Risk

  • Risk register updated after Identify Risks.
  • Qualitative = probability-impact matrix; Quantitative = Monte Carlo, decision tree.
  • Risk response: choose reliable vendor = mitigation.
  • Risk Breakdown Structure (RBS) categorizes risks.
  1. Procurement

  • Procurement SOW: specs, quantity, quality, performance data, period & place of performance.
  • RFP must balance detail with flexibility for seller innovation.
  1. Stakeholders

  • New stakeholders appear at phase gates, personnel changes, or re-orgs → update Stakeholder Register.
  • High-power/low-interest → keep satisfied; low-power/high-interest → keep informed.
  • Stakeholder engagement assessment matrix compares current vs. desired participation.
  • Project charter captures high-level needs from key stakeholders.
  1. Agile Highlights

  • Product roadmap precedes release plan; release plan precedes iteration plan.
  • Definition of Done (DoD) checklist gates every increment.
  • Task board visualizes To-Do / In-Progress / Done.
  • Fist-to-Five consensus: ≥3 fingers = agreement.
  • Timeboxed iterations cannot be extended; new work waits for next sprint.
  • Product Owner alone accepts or rejects work.
  1. Tools Quick Reference

  1. Exam Answering Strategy

  1. "What should the PM do FIRST?" → choose the earliest process step.
  2. "What should the PM do NOW?" → pick the most comprehensive, compliant option.
  3. Future-oriented questions → look for lessons learned.
  4. Preventive focus → select the proactive, best-practice answer.

Tags: PMP PMBOK project-management agile risk-management

Posted on Mon, 11 May 2026 01:02:35 +0000 by cHinshaw